July 20, 2001
Wabamun Decision
The attached document is the Power Pool Council's decision as Balancing Pool Administrator regarding TransAlta Utilities Corporation's force majeure and High Impact/Low Probability (HILP) claims pursuant to the Power Purchase Arrangement for the Wabamun 4 generating unit.
Power Pool Council Decision: TransAlta's force majeure claim for Wabamun 4 generating unit